Andy C. answered 11/02/17
Tutor
4.9
(27)
Math/Physics Tutor
Working together: 1/12 roofs per hour
First roofer: 1/16 roofs per hour
X + 1/16 = 1/12
x = 1/12 - 1/16 = 4/48 - 3/48 = 1/48
Together, they work 1/48 + 1/16 = 1/48 + 3/48 = 4/48 = 1/12
It will take the second roofer 48 hours