Mahendra K. answered 06/17/15
Tutor
New to Wyzant
Experienced Engineer , Mathematics and Hindi Tutor
A man can lay a concrete sidewalk in 5 days which means 1/5 sidewalk per day
Similarly, his assistant can lay same sidewalk in 8 days means 1/8 side walk per day.
Both of them working together will complete (1/5+1/8) = 13/40 side walk in a day
Both of them worked together for 2 days and completed 2*13/40 =26/ 40 side walk
After 2 days left over side walk is 1-26/40= 14/40
Days taken by Assistant to finish left over sidewalk is= (14/40) / (1/8)
=( 14*8) / (40*1) = 14/5= 2.8 days
The Assistant will finish leftover sidewalk in 2.8 days