First, let's convert everything to yards. There are 3 feet in a yard, so:
30 feet = 30/3 yards = 10 yards
21 feet = 21/3 yards = 7 yards
6 feet = 6/3 yards = 2 yards
Next we'll find the volume of the foundation. Volume = length×width×depth, so:
V = 10×7×2 = 140 cubic yards
Since each truck holds 7 cubic yards of dirt, we need 140/7 = 20 truck-loads to haul all of the dirt.