Raymond B. answered 02/03/22
Math, microeconomics or criminal justice
T = kL/W
120 = 20k/10
120 = 2k
k = 60 = constant of variation
T = 60L/W
T =60(20)/(10-2) = 120/8 = 15 day if 2 workers are out
double length with 16 workers
T= 60(40)/16 = 150 day
for 30 day months 150 days = 5 months. It won't be ready in 4 months
T = 2 months = 60 days = 60(20)/W
60=1200/W
W =1200/60 = 20
W = 20 workers to finish 20 m in 2 months