The table below represents a IS project set of activities, its expected completion time (weeks) and preceding activities.

Activity Expected Time (weeks) Preceding activities
A 5 None
B 4 None
C 10 A
D 8 B
E 14 B
F 6 C, D
G 7 D, E, F
H 3 F, G


a Draw a network diagram for the IS project shown above. For each activity, calculate its earliest completion time (TE) and latest completion time (TL). Label TE and TL on the network diagram.

b.     Calculate the slack time for each activity.

c.     List the activities on the critical path.

The project has started, and the project team members have just completed activity

D. Activity D took 9 weeks to complete, which is longer than the expected time allocated. Will this affect the overall project schedule? Explain your answer


1 Expert Answer

By:

Still looking for help? Get the right answer, fast.

Ask a question for free

Get a free answer to a quick problem.
Most questions answered within 4 hours.

OR

Find an Online Tutor Now

Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.