Inactive Tutor answered 01/11/18
Tutor
New to Wyzant
The job needs 480 man/hours (12 * 8 * 4)
5 people at 6 hours produce 30 man/hours
480 / 30 = how many days?
Niamh S.
asked 01/11/18Inactive Tutor answered 01/11/18