Raymond B. answered 03/10/23
Math, microeconomics or criminal justice
42x12x6 ft = 14x4x2 yd = 112 yd^3
112/8= 14 truck loads
14x$20= $280= otal cost
or
42x12x6= 3024 ft^3
8 yd^3= 3^3 x 8 ft^3 =27x8= 216 ft^3
3024/216= 14 truck loads
14x20 = $280
Whytni S.
asked 03/10/23A building contractor is to dig a foundation
42
feet long,
12
feet wide, and
6
feet deep. The contractor pays
$20
per load for trucks to remove the dirt. Each truck holds
8
cubic yards. What is the cost to the contractor to have all the dirt hauled away?A building contractor is to dig a foundation
42
feet long,
12
feet wide, and
6
feet deep. The contractor pays
$20
per load for trucks to remove the dirt. Each truck holds
8
cubic yards. What is the cost to the contractor to have all the dirt hauled away?
Raymond B. answered 03/10/23
Math, microeconomics or criminal justice
42x12x6 ft = 14x4x2 yd = 112 yd^3
112/8= 14 truck loads
14x$20= $280= otal cost
or
42x12x6= 3024 ft^3
8 yd^3= 3^3 x 8 ft^3 =27x8= 216 ft^3
3024/216= 14 truck loads
14x20 = $280
Get a free answer to a quick problem.
Most questions answered within 4 hours.
Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.