Raymond B. answered 07/21/22
Math, microeconomics or criminal justice
15 farmers do the work in 20 days
5 farmers take 3 times as long to do the work in 60 days
7 students do the work in 60 days
14 students do the work in 30 days
in 9 days 14 students do 9/30 = 3/10 of the work
in 9 days 15 farmers do 9/20 of the the work
in 9 days together they do 3/10+9/20 = 6/20+9/20 = 15/20 =3/4 of the work
in another 5 days the farmers, without the students will do 1/4 of the work
1/4+3/4 = all the work
with students working 9 days and farmers working 14 days, they'll finish the work