24 hours, for 4 painters to paint 4 walls
It took 8 painters 6 hours to paint 2 walls
4 painters would take twice as long to paint 2 walls, for 12 hours
It would take twice as long for 4 painters to paint 4 walls: 12x 2 = 24 hours