Hailey S.

asked • 12/03/19

The amount of time to complete a job varies inversely with the number of workers. Forty-two workers can finish a job in 18 days. How many days would it take 54 workers to complete the same job?


A) 8 days

B) 14 days

C) 23 days

D) 126 days


1 Expert Answer

By:

Still looking for help? Get the right answer, fast.

Ask a question for free

Get a free answer to a quick problem.
Most questions answered within 4 hours.

OR

Find an Online Tutor Now

Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.