William B. answered 01/14/15
Tutor
New to Wyzant
Patient, Engineer/Biotech for Math, Microsoft Excel, Word Process
5/4 sq yds = x sq yds
1/3 hr 1 hr
or
5/4 sq yds x 1 hr = x sq yds x 1/3 hr
then
x = 5/4 sq yds x 1 hr = 5/4 sq yds x 1 hr x 3 the hr units cancel out
1/3 hr 1 hr
leaving
x = 5 sq yds x 3 = 15 sq yds = 3.75 sq yds per hr
4 4