Assume that you have a normal distribution representing the likelihood of completion times. The mean of the distribution is 10, and the standard deviation is 3. True or False: The probability of completing the project in 8 or fewer days is the same as the probability of completing the project in 18 days or more.

1 Expert Answer

By:

Byron S. answered • 11/23/14

Tutor
5.0 (44)

Math and Science Tutor with an Engineering Background