
Andy C. answered 08/11/18
Tutor
4.9
(27)
Math/Physics Tutor
Recall that if they job can be done in T hours, then the workrate is 1/T jobs per hour.
Their respective speeds are 1/P , 1/S, 1/I
Their combined workrate speed is 1/20, so 1/P + 1/S + 1/I = 1/20; this is the 1st equation
1/P+ 1/S = 1/30 <--- Peter and simon finish the job is 30 hours; this is the 2nd equation
1/S + 1/I = 1/40 <--- Simon and Ian can complete the job is 40 hours; this is the 3rd equation
Equation #1 MINUS Equation 2:
1/I = 1/20 - 1/30 = (30 - 20)/600 = 10/600 = 1/60
I=60
Ian can complete the job in 60 hours working alone.
Equation 1 MINUS Equation 3:
1/P = 1/20 - 1/40 = (40-20)/800 = 20/800 = 1/40
P = 40
Peter can do the job in 40 hours working alone.
1/40 + 1/S + 1/60 = 1/20
3 + 120/s + 2 = 6 <--- multiplies everything by 120
120/s = 1
s = 120
Simon can complete the job in 120 hours working alone.