Andrew M. answered 11/06/17
Tutor
New to Wyzant
Mathematics - Algebra a Specialty / F.I.T. Grad - B.S. w/Honors
4 hours for 10 workers means 1 worker
would take 40 hours ... each worker does
1/40 of the job per hour
8 workers will do 8/40 or 1/5 per hour
so it will take 5 hours for 8 workers to
do the job.