Mark M. answered 06/18/20
Mathematics Teacher - NCLB Highly Qualified
If the job is completed in two weeks, 14 days, then 29 crews are needed (400 / 14 = 28.57142857)
$16000 + (29)($14000) + (14)($3000)
If the job is completed in one week, 7 days, then 58 crews are needed (400 / 7 = 57.15428514)
$16000 + (58)($14000) + (7)($3000)
If the job is completed in 3 days, then 134 crews are needed (400 / 3 = 133.3333)
$16000 + (134)($14000) + 3($3000)