LG S.

asked • 04/13/19

Rest of the question is listed below in the Description

a proposed job has estimated direct costs of $35,239. Company overhead is estimated to be 11% and project overhead is typically 7.5% of all sales. If the desired profit on the project is 15%, what should the bid price be?

1 Expert Answer

By:

Terry F. answered • 04/13/19

Tutor
4.9 (323)

PhD, MBA, MA(math) Math, Statistics, Economics,Finance, Physics, Comp.

Still looking for help? Get the right answer, fast.

Ask a question for free

Get a free answer to a quick problem.
Most questions answered within 4 hours.

OR

Find an Online Tutor Now

Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.