Raymond B. answered 04/04/23
Math, microeconomics or criminal justice
A lays 33 1/3 per hour
B lays 37 1/2 per hour
together they lay 70 5/6 per hour
together they lay 850 in 850/(70 5/6) hours
= 850(6/425) = 12 hours
Re L.
asked 09/13/21If a takes 3 hours to lay 100 brick and B takes 4 hours to lay 150 bricks how long does it take them together to lay 850 bricks
Raymond B. answered 04/04/23
Math, microeconomics or criminal justice
A lays 33 1/3 per hour
B lays 37 1/2 per hour
together they lay 70 5/6 per hour
together they lay 850 in 850/(70 5/6) hours
= 850(6/425) = 12 hours