Anthony T. answered 11/26/20
Patient Science Tutor
a. If there were no friction, the pusher would have to overcome a force due to gravity of 33.3 kg x 9.8 m/s2 x sin28° or 153.2 N. The work done going up the slope is 153.2 n x 12.3 m = 1884 J. As the actual force needed was 222 N, the total work done was 222 N x 12.3m = 2730 J. The difference between 2730 J and 1884 J is the work done to overcome friction or 846 J.
b. The work necessary to lift the carton 1.33 m is 33.3 kg x 9.8 m/s2 x 1.33 m = 434 J.
c. Power is the rate of work J/s, so 434 J/2.55 s = 170 watts.
As always, check the math and reasoning.