Two crews working toward each other are 13.75miles apart. One crew paves 1.3 lies of highway per day the other paces 1.2. How long will it take them to meet?

1 Answer by Expert Tutors

Tutors, sign in to answer this question.
Mark M. | Math Tutor--High School/College levelsMath Tutor--High School/College levels
4.9 4.9 (821 lesson ratings) (821)
0
Let x = number of days it takes 
 
Then, 1.3x + 1.2x = 13.75
 
                    2.5x = 13.75
 
                        x = 5.5 days