The total work completed after 2min is: 2/15 + 2/20 + 2/30
The total work completed after 6min is: 2/15 + 6/20 + 6/30 as A has already left. This is also the time B leaves.
2/15 + 6/20 + 6/30 = (8+18+12)/60 = 38/60 = 19/30
Since C completes 1/30 per minute, C will need (30/30-19/30) / (1/30) = (11/30) / (1/30) = 11 minutes to complete the task.