3 days ------------> x workers ;
12 days------------> 5 workers ;
12/3 = x/5 ⇔ 4 = x/5 ⇒ x = 20 workers. More workers reduce the duration for completing the same task.
Divide the number of days by 4; multiply the number of workers by 4.