Search 81,287 tutors
Ask a question
0 0

It takes lorraine 6 hours or Rocio 10 hour to complete a project alone. how long sould it take them to complete a project together?

Tutors, please sign in to answer this question.

2 Answers

Lorraine's productivity is (1 project/6 hours) or 0.1667 projects per hour
Rocio's productivity is (1 project/10 hours) or 0.1 projects s per hour
If t is the time (in hours) it would take them to complete one project while working together, then
(0.1667 projects/hr)*t + (0.10 projects/hr)*t = 1
t*(0.1667 + 0.1) = 1
t*(0.2667) = 1
Therefore t =  3.75 hours
x=# of hours together to complete a project
Lorraine completes 1/6 of the project in an hour
Rocio completes 1/10 of the project in an hour
(1/6)x+(1/10)x=1(completed project)
multiply both sides of the equation by LCM of 6 and 10 which is 30
x=3 and 6/8
x=3 and 3/4 or
x=3.75 hours