8 men build a chalet in 18 days. How long will it take 12 men?
First of all, we know 12 men are more than 8 men so whatever answer we get has to be less than 18 days. So we set up the equation like this:
a. 8men * 18 days = 12 men * X days
8*18 = 12*X
144 = 12X
144/12 = 12X/12
12 = X
So it would take 12 men 12 days.
b. 5 men?
Set up the equation the same way.
8 men * 18 days = 5 men * X days
8*18 = 5X
144 = 5X
144/5 = X
28.8 = X
It will take 5 men 28.8 days.
c. How many men would build the chalet in 3 days?
Again, set up the equation the same way.
8men * 18 days = X men * 3 days
8*18 = X*3
144 = 3X
144/3 = 3X/3
48 = X
It will take 48 men 3 days to build the chalet.