One grocery clerk can stock a shelf in 45 min.

A second clerk requires 40 min to stock the same shelf. How long would it take to stock the shelf if the two clerks worked together?

1 Expert Answer

By:

Christopher R. answered • 11/20/14

Tutor
4.8 (84)

Mobile Math Tutoring

Bill P.

There is a mistake in the above solution. 45t + 40 t = 85t, not 95t.
 
Thus t = 1800/85 or about 21.18 minutes.
 
Note: I knew there was a mistake when a saw the answer was less than 20 minutes. It would take exactly 20 minutes to complete this task if each clerk could complete this task in 40 minutes alone. Since the one clerk is a bit slower, it must take more than 20 minutes (but also less than 22.5 minutes (half of 45 minutes) ) 
Report

04/05/15

Christopher R.

I'm bad. I just made a simple arithmetic error. 40 +45=85, not 95. Hence, 85t=1800 in which t=21.18 minutes. 
Report

04/05/15

Still looking for help? Get the right answer, fast.

Ask a question for free

Get a free answer to a quick problem.
Most questions answered within 4 hours.

OR

Find an Online Tutor Now

Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.