Arthur D. answered 01/29/17
Tutor
4.9
(306)
Mathematics Tutor With a Master's Degree In Mathematics
men work 1.2 times the rate of women
8 men and 12 women is the same as 8 men and 10 men (instead of 12 women-10*1.2=12)
18 men do the job in 6 days
how many men does it take to do the job in 4 days ?
6/4=1.5
1.5*18=27 men to do the job in 4 days
also, this is an inverse proportion or inverse variation; y=k/x
18 men in 6 days, how many men in 4 days ?
18=k/6
k=18*6
k=108
y=108/4
y=27 men