Isaac C. answered 11/10/16
Tutor
4.9
(823)
Physics, Chemistry, Math, and Computer Programming Tutor
Since there is no friction, the amount of work required is simply given by the change in potential energy. The height of the ramp is given by 80m * sin 30 = 40 meters. So the amount of work done is given by 80m * 62kg *9.8 m/s2 = 24.3kJoules