Raymond B. answered 03/13/22
Tutor
5
(2)
Math, microeconomics or criminal justice
1/9 + 1/6 = 1/t, t= time it takes for both working together
multiply both sides by 18t to eliminate the fractions
2t + 3t = 18
5t = 18
together they can lay the slab in 18/5 = 3.6 hours
3.6 x 47 = $169.20 labor estimate for the job if both work together