Sanjay S. answered 02/04/15
Tutor
4.9
(34)
Expert, Patient and Motivated Tutor for Math, Science and Test Prep
Happy,
Volume of shed is 3.8 cu m
55% is concrete so volume of concrete per base is 0.55*3.8 cu m
1 lorry delivers 6 cu m, 5 loads will be 6*5 = 30 cu m
Bases built with 6 loads = 30/(0.55*3.8) = 14.3
So 14 bases can be built.