Mark M. answered 02/01/18
Tutor
4.9
(953)
Retired Math prof with teaching and tutoring experience in trig.
Let x = number of hours it takes to drain the pool if both pumps are working
1/6 = portion drained by the first pump per hour
1/12 = portion drained by the other pump per hour
1/x = portion drained by both pumps per hour
1/6 + 1/12 = 1/x
Multiply by the LCD, 12x, to obtain 2x + x = 12
3x = 12
x = 4 hours