A can do a work in 6 days while B can do a work in 8 days.
6A = 1 {6 times A does 1 job}; so A = 1/6 {1/6 of job per day}
8B = 1 {8 times B does 1 job}; so B = 1/8 {1/8 of job per day}
They worked together for 2 days and B left the work.
2 x (1/6 + 1/8) = 1/3 + 1/4 = 4/12 + 3/12 = 7/12 {or 7/12 of the job is done in 2 days they work together}
This leaves 5/12 of the job remaining when B leaves.
How time will A require to complete the work?
Since A does 1/6 job per day we divide 1/6 into the remaining 5/12 or
[5/12] / [1/6] or 5/12 x 6/1 = 30/12 = 2.5 days