To determine whether overhead is overapplied or underapplied, we need to compare the actual overhead costs with the overhead applied using the predetermined activity-based costing (ABC) rates.
Step 1: Calculate the predetermined overhead rate for each cost pool.
The formula is:
Predetermined overhead rate = Anticipated cost / Total anticipated cost driver usage
We combine the anticipated driver usage from both plots.
1. Equipment Depreciation
Anticipated cost = $5,000
Total anticipated machine hours = 8,000 + 7,000 = 15,000 hours
Overhead rate = $5,000 / 15,000 = $0.333333 per machine hour
Actual machine hours = 7,500 + 6,000 = 13,500 hours
Applied overhead = ($5,000 / 15,000) × 13,500
Applied overhead = $4,500
Actual cost = $5,000
Underapplied overhead = $5,000 - $4,500 = $500
2. Fuel Expenses
Anticipated cost = $3,000
Total anticipated mileage = 10,000 + 8,000 = 18,000 miles
Overhead rate = $3,000 / 18,000 = $0.166667 per mile
Actual mileage = 9,000 + 12,000 = 21,000 miles
Applied overhead = ($3,000 / 18,000) × 21,000
Applied overhead = $3,500
Actual cost = $3,300
Overapplied overhead = $3,500 - $3,300 = $200
3. Scheduling Expenses
Anticipated cost = $50,000
Total anticipated orders = 40 + 40 = 80 orders
Overhead rate = $50,000 / 80 = $625 per order
Actual orders = 30 + 20 = 50 orders
Applied overhead = $625 × 50
Applied overhead = $31,250
Actual cost = $53,000
Underapplied overhead = $53,000 - $31,250 = $21,750
4. Meals and Lodging
Anticipated cost = $4,000
Total anticipated nights = 10 + 10 = 20 nights
Overhead rate = $4,000 / 20 = $200 per night
Actual nights = 15 + 8 = 23 nights
Applied overhead = $200 × 23
Applied overhead = $4,600
Actual cost = $4,500
Overapplied overhead = $4,600 - $4,500 = $100
Step 2: Calculate total actual and applied overhead.
Total actual overhead:
$5,000 + $3,300 + $53,000 + $4,500 = $65,800
Total applied overhead:
$4,500 + $3,500 + $31,250 + $4,600 = $43,850
Step 3: Calculate the difference.
Underapplied overhead = Actual overhead - Applied overhead
Underapplied overhead = $65,800 - $43,850
Underapplied overhead = $21,950
Final Answer: $21,950 UNDERAPPLIED overhead.
This means Towering Inc. incurred $21,950 more in actual overhead costs than it assigned to its timber operations using its predetermined ABC rates.
Remember:
- Underapplied overhead occurs when actual overhead exceeds applied overhead.
- Overapplied overhead occurs when applied overhead exceeds actual overhead.
We also followed the problem's rounding instructions by keeping the overhead rates unrounded during calculations and rounding only the final amount for each cost pool.