We have 19/6 times as many workers, so it should take 6/19 the amount of time.
6/19 · 57 = 18 days
Or, set it up as follows: Total work to complete project (as measured in worker days) = 6 · 57 = 19 · x
Here, the time it takes is inversely proportional to the number of workers. This means that the product of those two quantities is constant.