the number of days required to build is the number of workers. One house was built in 57 days by 6 workers. How many days would it take to build a similar house with 19 workers?

2 Answers By Expert Tutors

By:

James E.

Wow thanks
Report

11/18/21

Josh F.

tutor
My pleasure — 2 formulas worth remembering: When y is directly proportional to x, we get … y/x = k (constant) When y is inversely proportional to x, instead we have … xy = k
Report

11/18/21