BJ A. answered 06/10/21
Experienced co-founder & Product Manager (CPM) / Project Manager (PMP)
100 parts were produced in 1 hour
Increase in productivity = 20%
New productivity:
100 x (1 + 0.2) = 100 x 1.20 = 120
120 parts would be produced in 1 hour
Number of hours the plant would have to work to produce 1000 parts = 1000/120 = 8.33 hours
E) between 8 and 9 hours