Michael F. answered 07/11/19
Each day P does 1/15th of the work
Each day Q does 1/24th of the work
Working together, each day they do 1/15 +1/24 of the work, that is 39/360 or 13/120 of the job per day
Working four days they do 52/120 or 13/30 of the job, so that 17/30 of the job is left over.