Machines X and Y work at their constant rates. How many more hours does it take machine Y to fill an order of a certain size than it takes machine X?

Machines X and Y work at their constant rates. How many more hours does it take machine Y to fill an order of a certain size than it takes machine X?
(1) Machines X and Y, working together, fill a production order of this size in two-thirds the time that machine X, working alone, does.
(2) Machine Y, working alone, fills a production order of this size in twice the time that machine X, working alone, does.
Given the above, what is true?
A.if statement (1) by itself is sufficient to answer the question, but statement (2) by itself is not;
B. if statement (2) by itself is sufficient to answer the question, but statement (1) by itself is not;
C.if statements (1) and (2) taken together are sufficient to answer the question, even though neither statement by itself is sufficient;
D.if either statement by itself is sufficient to answer the question;
E.if statements (1) and (2) taken together are not sufficient to answer the question, requiring more data pertaining to the problem

1 Expert Answer

By:

Pradip M. answered • 05/16/18

Tutor
4.8 (15)

Increase your Thinking & Knowledege Quotient (TKQ)

Still looking for help? Get the right answer, fast.

Ask a question for free

Get a free answer to a quick problem.
Most questions answered within 4 hours.

OR

Find an Online Tutor Now

Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.