This is a "weighted average" calculation. Let E = the average production capacity for the hour (efficiency). Since the production line ran at 75% for 20/60 = 1/3 of the hour, 75% is weighted at 1/3. Since the line ran at 53% for the remaining 40/60=2/3 of the hour, 53% is weighted at 2/3:
E = (1/3)(75%) + (2/3)(53%)
E = 25% + 351/3%
E = 601/3% of capacity for the hour