Mark M. answered 10/22/16
Tutor
5.0
(278)
Mathematics Teacher - NCLB Highly Qualified
In the first four days:
4/18 + 4/27 + 4/36
24+/108 + 16/108 + 12/108
52/108 of the job has been completed
In the last 7 days M does 7/36, or 21/108
52/108 + 21/108
73/108 is completed
35/108 is done by K and M.
x/27 + x/36 = 35/108
4x + 3x = 35 LCD 35
7x = 35
x = 5
Total time, 4 days (the start) + 5 days (K & M) + 7 days (M alone)