A does 1/9 of the job in one day
B does 1/14 of the job in one day
x=# of days working together
(1/9)x+(1/14)x=1 job finished
(x/9)+(x/14)=1
multiply by 126 on both sides (the LCM)
14x+9x=126
23x=126
x=126/23
x=5.478 days together (round as you like)