V= volume of the pond
V= x. t1 x=flow rate of slow pipe, t1= time that slow pipe needs to fill the pond
V= y. t2 x=flow rate of fast pipe, t2= time that fast pipe needs to fill the pond
y=3x
V= (x+y).12= 4x.12=48x
x= V/48
for fast pipe
V=3.V.t2/48
t2=48/3=16hr