1/6 + 1/4 = 1/x
The common denominator is 24x. Once we apply it, we only need the numerators.
4x + 6x = 24
10x = 24
x = 2.4 days
0.4(24) = 9.6 hours
0.6(60) = 36 mins
2 days, 9 hours, 36 mins
Brian B.
asked 03/13/20A person can do a job in 6 days. Another can do the same job in 4 days. If they work together, how long do they need to finish the job?
1/6 + 1/4 = 1/x
The common denominator is 24x. Once we apply it, we only need the numerators.
4x + 6x = 24
10x = 24
x = 2.4 days
0.4(24) = 9.6 hours
0.6(60) = 36 mins
2 days, 9 hours, 36 mins
John M. answered 03/13/20
Math Teacher/Tutor/Engineer - Your Home, Library, MainStreet or Online
1st person can do 1/6th of the job in one day.
2nd person can do 1/4 of the job in one day.
Together they can do 1/6 + 1/4 = 2/12 + 3/12 = 5/12 th of the job in one day,
so it will take them 12/5 or 2.4 days to complete the job.