asked 06/11/19After making changes in the Assign Resources dialog box, you can verify the cost and work values in which of the following dialog boxes?
A) Project Options: Scheduling
B)WBS Code Definition
C)Assignment Information
D)Custom Fields
Gurpreet Singh R. answered 05/26/25
Boost your tech confidence With me
C)Assignment Information