Elaine J. answered 03/10/24
PMP Exam Prep Coach with 95% Success Pass Rate
This answer is in the PMBOK in the COST MANAGENENT knowledge area.
answer --> cost performance index CPI
It measures the cost efficiency for work completed
- measurements lower than 1.0 = cost overrun -> you have spent more than your budget
- measurements more than 1.0 = cost underrun -> you have yet to spend up to your budget
- measurements of 1.0 = for work delivered, you have achieved equal value in cost, 1:1
When we cover this segment of knowledge there will be many examples covered and you will be encouraged to depend of cases from current and past projects to drive your knowledge of understanding
this for the PMP Exam and for used on future project work.
The training you do for your PMP is not only for the sake of passing an exam!
This training and others are to prepare you to deliver best project results for your organization.
I look forward to sharing my passing solutions for project management PMP Exam with you,
Students that proclaim to 'hate math'.... slip up and state they love doing problems with math solutions.
It is all about having the right instructor teaching the right materials.
Elaine Jackson, BS, PMP, GPM-b, CB-PMO
Holistic Project Management Consulting
Elaine J.
#1 lesson is to engage with lessons. A teacher can only teach and measure teaching ability based on feedback from students. We look forward to engagement with you and with your project team.03/18/24