The Question is not presented very well. The numbers are scattered all over and it doesn't offer any meaningful information. The candidate must present the numbers very well
Jane S.
asked 01/30/17Given the project depicted below, calculate PV, EV, CV, SV, CPI, and SPI for each activity. For the entire project, calculate EV, PV, AC, BAC, CV, SV, CPI, and
Earned Value Status Exercise
Given the project depicted below, calculate PV, EV, CV, SV, CPI, and SPI for each activity. For the entire project, calculate EV, PV, AC, BAC, CV, SV, CPI, and SPI. Is the project ahead or behind schedule? Is the project over or under budget? Where would you investigate to ascertain if corrective action is necessary?
Save the solution for this assignment as it will be used again in Week 11
Task
Budget
Planned Percent Complete
Actual Percent Complete
EV
PV
AC
A
$4500
100%
100%
$4500
B
$6500
100%
100%
$8000
C
$4000
100%
100%
$3750
D
$8000
100%
80%
$7300
E
$7500
100%
90%
$6150
F
$6000
30%
0%
$0
G
$2500
0%
20%
$250
H
$5000
0%
0%
$0
Given the project depicted below, calculate PV, EV, CV, SV, CPI, and SPI for each activity. For the entire project, calculate EV, PV, AC, BAC, CV, SV, CPI, and SPI. Is the project ahead or behind schedule? Is the project over or under budget? Where would you investigate to ascertain if corrective action is necessary?
Save the solution for this assignment as it will be used again in Week 11
Task
Budget
Planned Percent Complete
Actual Percent Complete
EV
PV
AC
A
$4500
100%
100%
$4500
B
$6500
100%
100%
$8000
C
$4000
100%
100%
$3750
D
$8000
100%
80%
$7300
E
$7500
100%
90%
$6150
F
$6000
30%
0%
$0
G
$2500
0%
20%
$250
H
$5000
0%
0%
$0
Follow
1
Add comment
More
Report
1 Expert Answer
Still looking for help? Get the right answer, fast.
Ask a question for free
Get a free answer to a quick problem.
Most questions answered within 4 hours.
OR
Find an Online Tutor Now
Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.