Given the project depicted below, calculate PV, EV, CV, SV, CPI, and SPI for each activity. For the entire project, calculate EV, PV, AC, BAC, CV, SV, CPI, and

Earned Value Status Exercise
Given the project depicted below, calculate PV, EV, CV, SV, CPI, and SPI for each activity. For the entire project, calculate EV, PV, AC, BAC, CV, SV, CPI, and SPI. Is the project ahead or behind schedule? Is the project over or under budget? Where would you investigate to ascertain if corrective action is necessary?

Save the solution for this assignment as it will be used again in Week 11
Task

Budget

Planned Percent Complete

Actual Percent Complete

EV

PV

AC

A

$4500

100%

100%





$4500

B

$6500

100%

100%





$8000

C

$4000

100%

100%





$3750

D

$8000

100%

80%





$7300

E

$7500

100%

90%





$6150

F

$6000

30%

0%





$0

G

$2500

0%

20%





$250

H

$5000

0%

0%





$0

1 Expert Answer

By:

Still looking for help? Get the right answer, fast.

Ask a question for free

Get a free answer to a quick problem.
Most questions answered within 4 hours.

OR

Find an Online Tutor Now

Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.