Microsoft Project Tutor with Extensive experience in Scheduling
- Apply a Gantt Chart view (from Task tab or View tab).
- Double-click anywhere in the chart portion of the Gantt Chart view (but not on individual bars) and click Bar Styles.
- In the Name field, click the type of Gantt bar (such as Task or Progress) that you want to format, and then click the Bars tab.
- If the Gantt bar type doesn't appear in the table, you can create a new Gantt bar for the task type you want.
- Under Start, Middle, and End, click the shapes, types or patterns, and colors for the bar.