
Sam S.
asked 02/06/17Why is a risk plan developed prior to completing the estimate? Give examples of planning (or not planning) for risk in a budget and how that impacted the execu
1 Expert Answer
We want the cost budget estimates to be as realistic and reliable as much as possible.
So, it is important to consult the risk register to identify all the cost risks that can impact the cost estimates and make cost provision for their mitigation in the cost estimating process.
Some of the examples of cost estimates risks that you need to plan for are as follows, Poor Scope Definition, Unforeseen works, Inclement Weather Events, Social Upheavals, Additional Works, Work Suspensions, Delays etc
So, you need to provide a contingency fund in the cost estimates to be used to mitigate these identified cost risks in case they become issues.
If you don't plan for these cost estimates risks and make contingency provision for them you will end up with surprises and excessive cost overruns which will not go down well with the client.
Still looking for help? Get the right answer, fast.
Get a free answer to a quick problem.
Most questions answered within 4 hours.
OR
Choose an expert and meet online. No packages or subscriptions, pay only for the time you need.
Carrie G.
05/14/22