Ademuyiwa S. answered 10/23/19
Experienced maths tutor
Hello friend,
Let T be the time and L be the Labour (Number of people working on the bridge)
Solving;
T∞ 1/√L (Inverse relationship)
T=K/√L (Constant "K" is introduced once the variation sign (∞) changes to equality (=) sign)
Where T = 75 and L = 9
75= K/√9
75= K/3
K= 225
First, the relationship between these variables is T=225/√L
Therefore, how long it will take 25 people to d it means that we should look for the time.
T=225/√L
T= 225/√25
T= 225/5
T= 45 days.
QED